PMCH Patna Parking Expansion: People using the Patna Medical College & Hospital (PMCH) may soon see improvements in parking provision and the requirement for patients and others to travel in order to gain access to expert care. In December 2026, PMCH will begin to utilise the final two phases of its multi-level car park. Furthermore, the much-anticipated super specialty hospital is due to start operating in January 2027.
PMCH Multi Level Park
In addition to the current PMCH multi-level car park which can hold around 750 cars and which is already in use by post-graduate doctors; PMCH is set to activate the final two phases.
The present car park is open 24 hours a day. It also comes with an electronic system to track cars and around 15 security personnel are in place to further safeguard cars.
Following activation of the additional car park phases, it is anticipated that PMCH staff, patients’ relatives and visitors will enjoy a structured parking service provided by the hospital. This should subsequently help to alleviate road and area usage within the hospital grounds.
Patna Momo Outlets Raided: 22 Kg Rotten Chicken Found, 21 Litres of Burnt Oil Destroyed
Super Speciality Hospital
The PMCH super specialty hospital is anticipated to commence functioning in January 2027. Currently, building of this hospital is in the last phase of development, and a fresh body has been charged with completing the project in three months.
It is anticipated that this hospital will deliver highly specialised care in the following areas:
- Urology
- Neurology
- Neurosurgery
- Gastro-enterology
- Endocrinology
- Nephrology
“Patients will be formally introduced to our super speciality hospital in the new year,” stated PMCH Superintendent Dr Rajiv Kumar Singh.
He explained that although the building phase was in its last stage, the newly allocated body had been given a three-month timeframe to finalise work. As one month of this time has now elapsed, January 2027 continues to be the projected date by which the hospital will be prepared for operation.
Nine Storeys PMCH Building Aimed for Completion in June 2027
In addition to the aforementioned developments, PMCH is further developing its estate by building a nine-storey structure on the present Tata Ward site. This is due to be finished in June 2027.
Following commencement of operation of this new building, the overall number of beds available at PMCH is anticipated to rise to 2,100. Thus, the hospital should greatly increase its in-patient provision.
As December 2026 and January 2027 draw nearer, PMCH’s imminent developments are likely to constitute yet further key milestone in modernising the state’s largest government-run hospitals.